Description

An Audit Report will automatically be created for a G-Delta any time changes are detected within the base Database Schema for the defined time interval. Users can also request an Audit at any time by following the steps within this article. 


How to Request an Audit

  • In the Project Dashboard, locate the Project within the Projects Pane and click on the G-Delta icon for the Project.


  • Select a G-Delta within the G-Delta Management Dashboard. The selected G-Delta will be highlighted in blue.


  • Click on the Request Audit button within the G-Delta Audit Summary Pane.


  • Then, click Yes in the prompt window to request the audit.


  • The following message will appear in the upper right corner of the screen. The user who requested the audit will receive an email when the audit is available.